This project consists of improving the existing and deficient offset intersection geometry y upgrading 0.26 miles of New Albany-Condit Road and 0.19 miles of Walnut Street by constructing a modern 2×1 multilane roundabout at the intersection of New Albany-Condit Road and Walnut Street. The project also includes the installation of a culvert replacement, closed storm sewer system, street lighting, and various other improvements.
Next Steps
Upcoming work will include installation of concrete splitter islands, granite curb, asphalt paving, light poles, pavement markings, and signage.
Work Completed
Work completed includes the removal of the existing asphalt, excavation for the new box culvert, installation of the new box culvert and storm sewer system, installing underground electrical conduit, constructing the roadway embankment, and aggregate base.
Traffic Maintenance
The intersection of Walnut Street and New Albany-Condit Road remains closed until May 31, 2026.