Approximately 620 feet of storm sewer pipe was installed, and existing storm sewer structures were removed along Genessee Avenue and within the alley right-of-way. The new storm sewer was connected to the existing storm system on Earl Avenue. All disturbed pavement and vegetated areas were restored.
PROJECT UPDATE: Zuber Road – Plum Road Drainage Improvement Project
This project will improve approximately 8,206 feet of drainage along Zuber Road and Young Road by clearing and improving the drainage ditch, restoring its proper grade, and replacing and lowering culverts to improve stormwater flow.