West North Broadway Bridge 1.18 over Olentangy River

Rehabilitation of the West North Broadway 1.18 Bridge over the Olentangy River by applying a variable thickness overlay and installing a concrete barrier to provide a shared-use path on the south side of the bridge and sidewalk on the north side of the bridge. Other work includes converting the abutments to semi-integral, replacing bearings and approach slabs, and upgrading the existing wingwalls.
PROJECT TYPE:
Bridge
COST:
$2,862,930.42
BEGIN CONSTRUCTION DATE:
6/2/2025
FINAL COMPLETION DATE:
7/17/2026
MAINTENANCE OF TRAFFIC:
Traffic maintained during construction, reduced to one lane in each direction.
FUNDING:
Ohio Department of Transportation (ODOT) LBR funds, Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
Parsons
CONSTRUCTION CONTRACTOR:
Complete General Construction
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2025
LOCATION:
West North Broadway Bridge 1.18 over Olentangy River, between Milton Avenue and Ohio Health Parkway
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org