Walnut Street at New Albany-Condit Road (SR-605) Roundabout

Improving the existing and deficient offset intersection geometry by upgrading 0.26 miles of New Albany-Condit Road (SR-605) and 0.19 miles of Walnut Street by constructing a modern 2x1 multilane roundabout. The project also includes the installation of a culvert replacement, closed storm sewer system, street lighting, and various other improvements.
PROJECT TYPE:
Highway
COST:
$3,974,624.76
BEGIN CONSTRUCTION DATE:
3/2/2026
FINAL COMPLETION DATE:
10/31/2026
MAINTENANCE OF TRAFFIC:
- Full intersection closure with detour (75-day duration).
FUNDING:
DESIGN CONSULTANT:
The Kleingers Group
CONSTRUCTION CONTRACTOR:
Strawser Paving
CONSTRUCTION INSPECTOR:
Shaun Armstrong
CONSTRUCTION YEAR:
2026
LOCATION:
Intersection of New Albany-Condit Road (SR-605) and Walnut Street
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org