McCoy Ditch Lateral 4 (West Broad Street to Norfolk Southern Railroad)

Replace approximately 4200 linear feet of tile originally constructed as Lateral 4 of the McCoy Petition.
PROJECT TYPE:
Drainage
COST:
TBD
BEGIN CONSTRUCTION DATE:
10/15/2026
FINAL COMPLETION DATE:
11/30/2026
MAINTENANCE OF TRAFFIC:
Traffic maintained.
FUNDING:
Drainage Engineer Funded, Private Developer
DESIGN CONSULTANT:
Franklin County Drainage Engineer
CONSTRUCTION CONTRACTOR:
Franklin County Drainage Utility Crew
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2026
LOCATION:
On the north side of West Broad Street approximately 4700' west of the intersection of Amity Road and West Broad Street.