Lockbourne Road (Magnolia Trail to Collings Drive) Pedestrian Improvements

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
Construct a 10-foot shared-use path from the intersection of the Magnolia Trail and Lockbourne Road north along the east side of Lockbourne Road to SR-317 and then east to Collings Drive. A portion of this path will be constructed by an adjacent development.

PROJECT TYPE:

Mobility

COST:

$975,460.00

BEGIN CONSTRUCTION DATE:

1/7/2030

FINAL COMPLETION DATE:

5/30/2031

MAINTENANCE OF TRAFFIC: 

Two-way one lane traffic permitted outside of peak hours.

FUNDING: 

COTA Transit-Supportive Infrastructure Funds, Village of Lockbourne

DESIGN CONSULTANT: 

OHM

CONSTRUCTION CONTRACTOR: 

TBD

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2030

LOCATION:

Lockbourne Road from the Magnolia Trail to SR-317 and SR-317 from Lockbourne Road to Collings Drive.