Leppert Road Bridge 1.48 SUP over Hayden Run

This is a pedestrian sidewalk connectivity project that will connect the Hilliard shared-use path to the City of Columbus sidewalk.
PROJECT TYPE:
Bridge
COST:
$242,320.00
BEGIN CONSTRUCTION DATE:
7/6/2026
FINAL COMPLETION DATE:
7/31/2026
MAINTENANCE OF TRAFFIC:
Southbound Lane Closure
FUNDING:
Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
CMT
CONSTRUCTION CONTRACTOR:
Franklin County Engineer - Bridge Maintenance
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2026
LOCATION:
Leppert Road Bridge 1.48 SUP over Hayden Run, between Arcadian Avenue and Hayden Run Road
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org