Kropp Road Drainage Outlet – Part 2

Replace approximately 3,710 linear feet of existing storm sewer with new storm sewer lines and structures along Krebs Ditch. Project begins at Hellbranch Run just east of Norton Road and extends to an existing catch basin just south of Kropp Road.
PROJECT TYPE:
Drainage
COST:
$2,083,285.00
BEGIN CONSTRUCTION DATE:
11/2/2026
FINAL COMPLETION DATE:
5/14/2027
MAINTENANCE OF TRAFFIC:
Norton Road to be closed to install road culvert; Date TBD.
FUNDING:
Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
Stone Environmental
CONSTRUCTION CONTRACTOR:
TBD
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2026
LOCATION:
Kropp Road
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org