Kropp Road Drainage Outlet – Part 1

Installation of approximately 1,800 linear feet of storm sewer pipe west of Rolling Hills Subdivision and south of Kropp Road heading east to Krebs Ditch. At crossings of public roads, traffic will either be maintained or detours will be established.
PROJECT TYPE:
Drainage
COST:
$1,038,067.00
BEGIN CONSTRUCTION DATE:
9/2/2025
FINAL COMPLETION DATE:
4/24/2026
MAINTENANCE OF TRAFFIC:
Closure of Kropp Road for up to two weeks
FUNDING:
Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
Stone Environmental
CONSTRUCTION CONTRACTOR:
Trucco Construction
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2025
LOCATION:
Pleasant Township - The section of the Krebs system covered by this plan is under the Rolling Hills subdivision flowing generally southeast under Rolling Hills Drive, Kropp Road and Norton Road on it way to the Hellbranch.
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org