Grove City Ditch Number 1

Remove approximately 550 linear feet of pipe and reestablish the grade and cross section of approximately 2500 linear feet of a petitioned ditch
PROJECT TYPE:
Drainage
COST:
TBD
BEGIN CONSTRUCTION DATE:
8/2/2027
FINAL COMPLETION DATE:
9/15/2027
MAINTENANCE OF TRAFFIC:
Traffic maintained.
FUNDING:
Drainage Engineer Funded
DESIGN CONSULTANT:
Franklin County Drainage Engineer
CONSTRUCTION CONTRACTOR:
Franklin County Drainage Utility Crew
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2027
LOCATION:
On the south side of Grove City Road between 4577 and 4861 Grove City Road.
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org