Ferris Road (Minnie Avenue to Cleveland Avenue)

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
This project involves 1.19 miles of improvements of Ferris Road from Karl Road to Cleveland Avenue. Improvements include pavement widening, resurfacing, two 5' wide sidewalks along the length of the corridor, lane restriping, straight curb, drainage improvements, intersection lighting, on-street parking facilities and bike lanes.

PROJECT TYPE:

Highway

COST:

$6,312,536.10

BEGIN CONSTRUCTION DATE:

3/1/2027

FINAL COMPLETION DATE:

5/26/2028

MAINTENANCE OF TRAFFIC: 

Phase 1 - Closure of Ferris Rd between Walford St & Cleveland Ave
Phase 2 - Closure of Ferris Rd between Minnie Ave and Walford St
Phase 3 - Final resurfacing & striping


FUNDING: 

Motor Vehicle Registration and Gas User Fees, Ohio Public Works Commission (OPWC),, Mid-Ohio Regional Planning Commission (MORPC) Funds

DESIGN CONSULTANT: 

ms Consultants

CONSTRUCTION CONTRACTOR: 

TBD

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2027

LOCATION:

Ferris Road between Minnie Avenue and Cleveland Avenue