Brown Road (Marsdale Avenue to Stimmel Road)

Reconstruct Brown Road between Marsdale Avenue and Stimmel Road/Linnet Avenue with curb and gutter, a 6' sidewalk and 10' shared-use path. A mini-roundabout will be constructed at the intersection of Brown Road and Hopkins Avenue.
PROJECT TYPE:
Highway
COST:
$8,993,375.38
BEGIN CONSTRUCTION DATE:
2/5/2029
FINAL COMPLETION DATE:
5/31/2030
MAINTENANCE OF TRAFFIC:
TO BE DETERMINED
FUNDING:
Ohio Department of Transportation (ODOT) Safety Funds, COTA Transit-Supportive Infrastructure Funds, Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
Carpenter Marty
CONSTRUCTION CONTRACTOR:
TBD
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2029
LOCATION:
Brown Road, between Marsdale Avenue and Stimmel Road / Linnet Avenue
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org