2026 Franklin County Resurfacing Program

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Upgrading 2.053 miles of various sections of Franklin County roadways including asphalt resurfacing, curb, and sidewalk replacement.

PROJECT TYPE:

Resurfacing

COST:

$998,531.10

BEGIN CONSTRUCTION DATE:

5/5/2026

FINAL COMPLETION DATE:

10/9/2026

MAINTENANCE OF TRAFFIC: 

Multiple short duration lane closures throughout Franklin County roadways.

FUNDING: 

Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

FCEO Internal

CONSTRUCTION CONTRACTOR: 

The Shelly Company

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2026

LOCATION:

Chatterton Road (Noe-Bixby Road to Fontaine Road), Winchester Pike (Noe-Bixby Road to Schirm Farms Way)

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org