2025 Franklin County Resurfacing Program

A maroon progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION, and COMPLETE. Only the COMPLETE stage has a checkmark, indicating completion.
Upgrading 4.918 miles of various sections of Franklin County roadways.

PROJECT TYPE:

Resurfacing

COST:

$2,217,301.23

BEGIN CONSTRUCTION DATE:

6/9/2025

FINAL COMPLETION DATE:

10/10/2025

MAINTENANCE OF TRAFFIC: 

Primarily flagger control. 

Road Closures: Leppert Road (20-days), Alkire/Demorest (5-days), and Morse/RNA (5-days).

FUNDING: 

DESIGN CONSULTANT: 

CONSTRUCTION CONTRACTOR: 

Kokosing Construction Company

CONSTRUCTION INSPECTOR: 

Mark Mullenax / Jesse Wahl

CONSTRUCTION YEAR: 

2025

LOCATION:

Alkire Road, Galloway, Ohio, 43119 Demorest Road, Grove City, Ohio, 43123 Galloway Road, Galloway, Ohio, 43119 Hall Road, Columbus, Ohio, 43228 Havens Corners Road, Blacklick, Ohio, 43004 Hilliard Cemetery Road, Hilliard, Ohio, 43026 Leppert Rd, Hilliard, Ohio, 43026 Morse Road, New Albany, Ohio, 43054 Norton Road, Columbus, Ohio, 43228 Rathmell Road, Columbus, Ohio, 43207 Reynoldsburg New Albany Roadd N, Blacklick, Ohio, 43004