Grove City Ditch Number 1

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
Remove approximately 550 linear feet of pipe and reestablish the grade and cross section of approximately 2500 linear feet of a petitioned ditch

PROJECT TYPE:

Drainage

COST:

TBD

BEGIN CONSTRUCTION DATE:

8/2/2027

FINAL COMPLETION DATE:

9/15/2027

MAINTENANCE OF TRAFFIC: 

Traffic maintained.

FUNDING: 

Drainage Engineer Funded

DESIGN CONSULTANT: 

Franklin County Drainage Engineer

CONSTRUCTION CONTRACTOR: 

Franklin County Drainage Utility Crew

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2027

LOCATION:

On the south side of Grove City Road between 4577 and 4861 Grove City Road.

CONTACT INFORMATION: 

Phone: 614-525-3030