Galloway Road (West Broad Street to Hall Road) Pedestrian Improvement

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
Construct an 11-foot shared-use path along the east side of Galloway Road from West Broad Street to Hall Road.

PROJECT TYPE:

Mobility

COST:

$3,295,050.00

BEGIN CONSTRUCTION DATE:

1/6/2031

FINAL COMPLETION DATE:

6/7/2032

MAINTENANCE OF TRAFFIC: 

Two-way one lane traffic permitted outside of peak hours.

FUNDING: 

COTA Transit-Supportive Infrastructure Funds, Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

2LMN, Inc.

CONSTRUCTION CONTRACTOR: 

TBD

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2031

LOCATION:

Galloway Road from West Broad Street to Hall Road

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org