2025 Safe Routes to Schools

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
Dunloe Elementary: Install 6’ walk connecting sidewalk along Dunloe Road to school. Install mid-block crossing on Sundale Place S. Install mid-block crossing, remove guardrail, and install sidewalk on Sundale Road. Madison Elementary: Relocate mid-block crossing on Madison School Drive. Sedalia Elementary: Install curb ramps at Arnsby Road and Negley Road. Install curb ramps at Everson Road W and Arnsby Road and relocate a mid-block crossing on Arnsby Road. Install curb extensions at school drives and relocate mid-block crossings across Sedalia Drive. Groveport Madison Middle School North: Install 5’ walk along south side of Sedalia Drive and relocate a mid-block crossing. Install crossings and curb ramps within school parking lot.

PROJECT TYPE:

Mobility

COST:

$457,200.00

BEGIN CONSTRUCTION DATE:

5/1/2028

FINAL COMPLETION DATE:

6/1/2029

MAINTENANCE OF TRAFFIC: 

Two-way one lane traffic permitted outside of peak hours.

FUNDING: 

DESIGN CONSULTANT: 

Toole Design Group

CONSTRUCTION CONTRACTOR: 

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2028

LOCATION:

Dunloe Elementary School, Madison Elementary School, Sedalia Elementary School and Madison Middle school North

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org