Zuber Road – Plum Run Drainage Section 3

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Replace and lower culverts under Zuber Road and Young Road.

PROJECT TYPE:

Drainage

COST:

$1,433,556.45

BEGIN CONSTRUCTION DATE:

4/13/2026

FINAL COMPLETION DATE:

3/12/2027

MAINTENANCE OF TRAFFIC: 

Concurrent Road Closures on Young Road and Zuber Road Summer 2026

FUNDING: 

["Ohio Department of Transportation (ODOT)","Ohio Public Works Commission (OPWC)","Motor Vehicle Registration and Gas User Fees"]

DESIGN CONSULTANT: 

CESO

CONSTRUCTION CONTRACTOR: 

V3 Construction Group Limited

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2026

LOCATION:

Jackson and Pleasant Townships immediately south of I-71

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org

DETOUR MAP