Amity Road Bridge 6.33 over Patterson Ditch

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
Full replacement of the existing corrugated metal pipe culvert by Franklin County Bridge Maintenance crews. The new structure will be a 10'x10' reinforced concrete box.

PROJECT TYPE:

Bridge

COST:

TBD

BEGIN CONSTRUCTION DATE:

6/1/2027

FINAL COMPLETION DATE:

7/16/2027

MAINTENANCE OF TRAFFIC: 

Full Closure

FUNDING: 

Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

BG Engineering

CONSTRUCTION CONTRACTOR: 

Franklin County Engineer - Bridge Maintenance

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2027

LOCATION:

Amity Road Bridge 6.33 over Patterson Ditch, between Morris Road and Patterson Road

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org