Woodrow Ditch

The current portion of the work on Woodrow Ditch is to clear 750' of ditch between Reaver Lane and SR 62. After clearing we will also attempt to locate a historic drainage tile that runs under a portion of this section of Woodrow.
PROJECT TYPE:
Drainage
COST:
$75,000.00
BEGIN CONSTRUCTION DATE:
11/3/2025
FINAL COMPLETION DATE:
5/1/2026
MAINTENANCE OF TRAFFIC:
Traffic maintained.
FUNDING:
Drainage Engineer Funded
DESIGN CONSULTANT:
In-House Design
CONSTRUCTION CONTRACTOR:
Franklin County Drainage Utility Crew
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2025
LOCATION:
In Franklin Township, from the north side of Reaver Lane to the west side of Harrisburg Pike (SR 62). Starting at 1476 Reaver and ending at 906 Harrisburg Pike.
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org