Kropp Road Drainage Outlet – Part 1

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Installation of approximately 1,800 linear feet of storm sewer pipe west of Rolling Hills Subdivision and south of Kropp Road heading east to Krebs Ditch. At crossings of public roads, traffic will either be maintained or detours will be established.

PROJECT TYPE:

Drainage

COST:

$1,038,067.00

BEGIN CONSTRUCTION DATE:

9/2/2025

FINAL COMPLETION DATE:

4/24/2026

MAINTENANCE OF TRAFFIC: 

Closure of Kropp Road for up to two weeks

FUNDING: 

Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

Stone Environmental

CONSTRUCTION CONTRACTOR: 

Trucco Construction

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2025

LOCATION:

Pleasant Township - The section of the Krebs system covered by this plan is under the Rolling Hills subdivision flowing generally southeast under Rolling Hills Drive, Kropp Road and Norton Road on it way to the Hellbranch.