Old Haughn Road Bridge 1.59 over Holton Run

Full in-house design replacement with precast deck slabs on Redi-Rock abutments.
PROJECT TYPE:
Bridge
COST:
$240,047.00
BEGIN CONSTRUCTION DATE:
5/5/2025
FINAL COMPLETION DATE:
6/18/2025
MAINTENANCE OF TRAFFIC:
Full Closure
FUNDING:
Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
Franklin County Engineer's Office
CONSTRUCTION CONTRACTOR:
Franklin County Engineer - Bridge Maintenance
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2025
LOCATION:
Old Haughn Road Bridge 1.59 over Holton Run
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org