Zuber Road – Plum Run Drainage Section 1

This project consists of 2,576 linear feet of drainage ditch improvements and profile grade restoration to address impairment by sediment deposition and allow major flood routing to function properly.
PROJECT TYPE:
Drainage
COST:
$398,500.00
BEGIN CONSTRUCTION DATE:
9/15/2025
FINAL COMPLETION DATE:
5/29/2026
MAINTENANCE OF TRAFFIC:
Traffic maintained.
FUNDING:
Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees
DESIGN CONSULTANT:
CESO
CONSTRUCTION CONTRACTOR:
V3 Construction Group Limited
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2025
LOCATION:
Jackson Township beginning at Plum Run approximately 2600' south of Zuber Road and 2350' west of Hoover Road and proceeding generally west under Ridpath Road and Seeds Road to end on the west side of Seeds Road.