Walnut Street at New Albany-Condit Road (SR-605) Roundabout

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Improving the existing and deficient offset intersection geometry by upgrading 0.26 miles of New Albany-Condit Road (SR-605) and 0.19 miles of Walnut Street by constructing a modern 2x1 multilane roundabout. The project also includes the installation of a culvert replacement, closed storm sewer system, street lighting, and various other improvements.

PROJECT TYPE:

Highway

COST:

$3,974,624.76

BEGIN CONSTRUCTION DATE:

3/2/2026

FINAL COMPLETION DATE:

10/31/2026

MAINTENANCE OF TRAFFIC: 

  • Full intersection closure with detour (75-day duration). 

FUNDING: 

DESIGN CONSULTANT: 

The Kleingers Group

CONSTRUCTION CONTRACTOR: 

Strawser Paving

CONSTRUCTION INSPECTOR: 

Shaun Armstrong

CONSTRUCTION YEAR: 

2026

LOCATION:

Intersection of New Albany-Condit Road (SR-605) and Walnut Street

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org