Renner Road (Alton & Darby Creek Road to Spindler Road)

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
This project consists of 0.75 miles of asphalt pavement widening and resurfacing of Renner Road between Alton & Darby Creek Road and Spindler Road. Improvements include earthwork, storm sewer, shared-use path, sidewalk, traffic signal, traffic control devices and the replacement of the existing bridge over Clover Groff Ditch.

PROJECT TYPE:

Highway

COST:

$4,820,239.45

BEGIN CONSTRUCTION DATE:

3/31/2025

FINAL COMPLETION DATE:

5/29/2026

MAINTENANCE OF TRAFFIC: 

Pre-Phase: Two-way one lane traffic maintained via flagger control
Phase 1: Westbound traffic maintained only
Phase 2: Full closure of Renner Road
Phase 3: Two-way traffic maintained
Phase 4: Two-way one lane traffic maintained via flagger control

FUNDING: 

Ohio Public Works Commission (OPWC), Private Developer, Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

EMH&T

CONSTRUCTION CONTRACTOR: 

J&J Schlaegel

CONSTRUCTION INSPECTOR: 

Kurt Selkinghaus

CONSTRUCTION YEAR: 

2025

LOCATION:

Renner Road between Alton & Darby Creek Road and Spindler Road

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org