Frank Road at Brown Road, Hardy Parkway Street, and Brown Road (Township)

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
This project consists of the construction of two multi-lane, standard-style roundabouts at the intersections of Frank Road & Hardy Parkway Street - Brown Road and Frank Road & Brown Road (Township). Improvements include a 10' wide shared-use path and 5' wide sidewalk, pedestrian refuges, lane reconfiguration, curb & gutter, drainage improvements, and intersection lighting.

PROJECT TYPE:

Highway

COST:

$8,924,851.03

BEGIN CONSTRUCTION DATE:

2/9/2026

FINAL COMPLETION DATE:

5/28/2027

MAINTENANCE OF TRAFFIC: 

Maintaining 1 lane in each direction on Frank Rd throughout construction, with independent closures of each side street being required. 
Phase 1 (90-days): North Leg
Phase 2 (30-days): Center
Phase 3A (45-days): South Leg
Phase 3B (10-days): South Leg at Certified Oil Driveway
Phase 3C (30-days): Hardy Parkway Street
Phase 4 (35-days): Frank Road splitter islands, intermediate course, center islands
Phase 5 (10-days): Final surface course, striping, signage

FUNDING: 

Ohio Department of Transportation (ODOT) Safety Funds, Ohio Public Works Commission (OPWC), Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

EL Robinson

CONSTRUCTION CONTRACTOR: 

Strawser Paving

CONSTRUCTION INSPECTOR: 

Kurt Selkinghaus

CONSTRUCTION YEAR: 

2026

LOCATION:

Frank Road at Brown Road, Hardy Parkway Street, and Brown Road (Township)