Cooke Road (Karl Road to Cleveland Avenue)

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Reconstruction of East Cooke Road from Karl Road to Cleveland Avenue (1.0 mile), including curb and gutter, 10' shared-use path on the north side of the road, 5' sidewalk on the south side of the road.

PROJECT TYPE:

Highway

COST:

$6,563,449.82

BEGIN CONSTRUCTION DATE:

3/2/2026

FINAL COMPLETION DATE:

5/28/2027

MAINTENANCE OF TRAFFIC: 

Phase 1 (75-days): 3/16/26 to 5/29/26
Phase 2 (75-days): 6/1/26 to 8/14/26
Phase 3 (75-days): 8/17/26 to 10/30/26

FUNDING: 

Mid-Ohio Regional Planning Commission (MORPC) Funds, Ohio Public Works Commission (OPWC), COTA Transit-Supportive Infrastructure Funds, Motor Vehicle Registration and Gas User Fees, Community Project Funding

DESIGN CONSULTANT: 

DLZ, Inc.

CONSTRUCTION CONTRACTOR: 

Shelly & Sands

CONSTRUCTION INSPECTOR: 

Tony McClendon

CONSTRUCTION YEAR: 

2026

LOCATION:

E Cooke Road from Karl Road to Cleveland Avenue

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org