Alum Creek Drive (London-Groveport Road (SR-317) to Groveport Road)

This project includes the widening of existing Alum Creek Drive (C.R. 122) from London-Groveport Road (SR-317) to Groveport Road, complete bridge replacement over Big Walnut Creek, roadway lighting, proposed drainage improvements as well as additional enhancements to improve pedestrian safety with a shared-use path and sidewalk the entire length of the corridor.
PROJECT TYPE:
Highway
COST:
$51,439,288.27
BEGIN CONSTRUCTION DATE:
8/30/2027
FINAL COMPLETION DATE:
5/31/2030
MAINTENANCE OF TRAFFIC:
Phase 1 (Fall 2027) - install NB Lt. Temporary Pavement to the extent possible with weather to facilitate shifting NB to west side of NB pavement.
Phase 2 (Winter 2027-Summer 2028) - Build NB Rt Bridge. Widen NB Rt pavement & build SUP.
Phase 3 (Summer 2028-Winter 2028) - Build NB Lt Bridge. Widen NB Lt median pavement.
Phase 4 (Winter 2028-Fall 2029) - Build SB Bridge, Widen SB Rt + Lt Pavement. All traffic NB side.
Phase 5 (Spring 2030) - Resurfacing, rebuild concrete medians at intersections.
FUNDING:
Federal Highway Administration BUILD grant, , Ohio Department of Transportation's Transportation Review Advisory Council (TRAC), Mid-Ohio Regional Planning Commission (MORPC) Funds, COTA Transit-Supportive Infrastructure Funds, Franklin County Transportation Improvement District, Central Ohio Transit Agency (COTA), City of Obetz, Madison Township, Private Developers, Motor Vehicle Registration and Gas User Fees, Community Project Funding
DESIGN CONSULTANT:
Stantec, Inc.
CONSTRUCTION CONTRACTOR:
TBD
CONSTRUCTION INSPECTOR:
Franklin County Engineer's Office
CONSTRUCTION YEAR:
2027
LOCATION:
Alum Creek Drive (C.R. 122) from London-Groveport Road (SR-317) to Groveport Road.