Alum Creek Drive (London-Groveport Road (SR-317) to Groveport Road)

A progress tracker with three stages: IN DESIGN (highlighted in red with a check mark), UNDER CONSTRUCTION (greyed out), and COMPLETE (greyed out).
This project involves 2.7 miles of improvements from London-Groveport Road (SR-317) to Groveport Road. Improvements include pavement widening, a 10' wide shared-use path and 8' wide sidewalk along the length of the corridor, lane restriping, curb and gutter, total bridge replacement over Big Walnut Creek, drainage improvements, signal improvements, and corridor-length lighting.

PROJECT TYPE:

Highway

COST:

$51,439,288.27

BEGIN CONSTRUCTION DATE:

8/30/2027

FINAL COMPLETION DATE:

5/31/2030

MAINTENANCE OF TRAFFIC: 

Phase 1 (Fall 2027) - install NB Lt. Temporary Pavement to the extent possible with weather to facilitate shifting NB to west side of NB pavement. 

Phase 2 (Winter 2027-Summer 2028) - Build NB Rt Bridge. Widen NB Rt pavement & build SUP. 

Phase 3 (Summer 2028-Winter 2028) - Build NB Lt Bridge. Widen NB Lt median pavement. 

Phase 4 (Winter 2028-Fall 2029) - Build SB Bridge, Widen SB Rt + Lt Pavement. All traffic NB side.

Phase 5 (Spring 2030) - Resurfacing, rebuild concrete medians at intersections.

FUNDING: 

Federal Highway Administration BUILD grant, , Ohio Department of Transportation's Transportation Review Advisory Council (TRAC), Mid-Ohio Regional Planning Commission (MORPC) Funds, COTA Transit-Supportive Infrastructure Funds, Franklin County Transportation Improvement District, Central Ohio Transit Agency (COTA), City of Obetz, Madison Township, Private Developers, Motor Vehicle Registration and Gas User Fees, Community Project Funding

DESIGN CONSULTANT: 

Stantec, Inc.

CONSTRUCTION CONTRACTOR: 

TBD

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2027

LOCATION:

Alum Creek Drive (C.R. 122) from London-Groveport Road (SR-317) to Groveport Road.

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org