2023 Community Development Block Grant Pedestrian Improvements

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Construct 4,100 feet of concrete sidewalk along both sides of the following streets in the Westbrook Subdivision: Westfield Drive, Westfield Drive South, Westfield Drive North, Marsdale Avenue, and Westbrook Drive. Work also includes curb ramps and driveway repairs. Construct 900 feet of concrete sidewalk along Chambers Road from Kenny Road to Hess Boulevard.

PROJECT TYPE:

Mobility

COST:

$1,307,824.95

BEGIN CONSTRUCTION DATE:

6/15/2026

FINAL COMPLETION DATE:

5/28/2027

MAINTENANCE OF TRAFFIC: 

Two-way one lane traffic permitted outside of peak hours.

FUNDING: 

Franklin County Community Development Block Grant, Motor Vehicle Registration and Gas User Fees

DESIGN CONSULTANT: 

In House - Westbrook/Proudfoot Associates - Chambers Road

CONSTRUCTION CONTRACTOR: 

Decker Construction

CONSTRUCTION INSPECTOR: 

Franklin County Engineer's Office

CONSTRUCTION YEAR: 

2026

LOCATION:

Westbrook Subdivision in Franklin Township, along the following streets: Westfield Drive, Westfield Drive South, Westfield Drive North, Marsdale Avenue, and Westbrook Drive. Chambers Road in Clinton Township from Kenny Road to Hess Boulevard.

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org